Our Addition
June 1: Ground Breaking
June 3:
The Footing is Poured
June 5:
The Foundation Wall is Poured
June 6: Molds Removed, Foundation Complete
June 8:
Foundation Inspected, Backfilled
June 10: Floor framed
June 12: Floor complete, covered for rain
June 13: Major flooding
June 15:
First three walls erected; Dumpster arrives
June 16-19: Second floor and second floor walls
June 22-26:
Roof framing